4/12/2020

Cost Management


Are you regularly involved in construction projects where having an accurate idea of costs is important? Most people in the construction industry and design professions would say yes, particularly if public funds are being used where there are specific funding limits.

For many design professionals, the pressure to deliver a project “within the budget” clouds objective decision making particularly during planning and design stage. Sometimes there is a stated assumption of “we can’t afford that” or a fear of “what happens if we come in over budget?” The way to confront these concerns head-on is with accurate cost information at each stage of the project.

During primary budgeting, the basic scope of the project needs to be defined, with as much detail as may be reasonable to help avoid overlooking critical components that need to be accounted for. For example, saying there is a need for higher class office space can produce a reasonable range of budget numbers, but if the need for a large, the temperature-controlled computer center is needed within that office space, and is not accounted for in budgeting, then there is a disconnect between program needs and budget. Similarly, indicating a need for storage space can be fairly straight forward unless the hazard level is overlooked and does not account for special types of construction or mechanical/ electrical requirements.


Cost planning is a statement of the proposed expenditure for each section of a building related to a standard or quality.

Cost Planning

The design has progressed now and information available such as:-
  1. Design team appointed including cost advisor
  2. Drawings - Site plan, floor plans, sections through the building and Elevations 
  3. Outline spec from client
  4. Detailed spec from architect
  5. Engineers/services engineers specification
  6. Ground reports
  7. Planning submitted
  8. Surveys carried out



The cost limit is established and split into cost targets. These targets are checked as the design

Figure - 01

Target Cost for Lump Sum Cost


Figure-02

The philosophy of cost planning can be divided into two main ideological groups;
  1. Costing a Design
  2. Designing to the Cost 
Costing a Design


Refers to methods of estimation that can arrive at a cost for a given (predetermined) design. Formal drawings need to be in existence for this process to function.

Designing to a cost

Guiding the development of a scheme so that it not only sets a budget amount but ensures the project does not exceed but provides the client with the greatest value for money possible.

Basic competences are;
  1. Understand the impact of early strategic decisions on project life cycle costs
  2. Recognize the importance of sustainability through a wider understanding of how buildings perform in use
  3. Harness benefits of interdisciplinary collaborative working with other professionals within the teams
  4. Engage with the design team
  5. Develop effective risk management strategies

Measurement for Cost Plan


Unit quantity and rate to tie up and Look at the units in the cost plan;

GF slab rn2, Pile caps-Nr, Ground beams-m, Piling-m
Frame tonnage plus fittings & secondary steelwork
Doors-Nr 
Windows-m2 or Nr
Upper floors- m2
Roof-m2 and Eaves, Verges, Ridges-m
External walls-m2 for different spec with deductions for openings
Internal walls-m2 with deductions for openings (optional)
Finishes-m2
Skirting, WW boards-m
Fittings-NrMechanical & Electrical m2 of GIA or a particular area
Builder’s work in connection % (BWIC)
External works m2 for the area of hard standings and landscaping and m for curbs etc..
Drainage and Incoming services Item
Preliminaries - %, cost/week, cost/month
Contingencies - %

Checking the Quantities

Check GIA against floor and ceiling finishes
Check ground floor area against GF GIA
Check upper floors against UF GIA
Roof area to building footprint or ground floor
Wall finishes are Ix ext wall areas + 2x internal walls and partitions
Where you have used GIA you have incorporated correct

Completing the rates

Use past BOQ with similar nature construction
Rebase the costs using indices for time and location/ Rebase them argument basis.
Ensure the rate reflects the unit of measurement
Check your inputting is a correct example; decimal point in the right place
Check formulas correct
Services and provisional sums
Some costs are cost/m2 of GIA some are cost/m2 of a specific area
Enter currency and unit to each item
Lump sums should be included as an Item
Line through all sums when entered into cost plan

Cross checking the cost plan to specification

     All spec items are included somewhere in the detailed cost - IF NOT either add in or exclude

     Check that all the relevant sections of the cost plan are completed


These are the area must include in the Front Sheet;

Title of the project, date report Number
Parties
Procurement route and program
Schedule of areas (GIA)/exclusions
Site area
Ratio of building footprint to the site area
Cost summary
Review example cost plan

Aim of Reports

To record the benchmarking process that you have carried out on your cost plan
To note the checks you have carried out and what changes you made as a result
You are accountable to the client!
Worth 40% of the assignment one mark

Content of Report

Summary of headline details of the cost Plan
Benchmarking of the cost/m2 against two or three other SFCA or cost Models
Identify the main cost areas through pie diagrams etc and compare to the above
Look at % totals
Pareto rule!!


Figure-03
Summary of Report

Explain if rates, location, specification etc caused variances
Explain if your costs were re-adjusted after this exercise
'Why' is important and 'how'
Justify your costs
Look at floor/wall ratios
Look at site coverage

Planning Remember!

Compare like with like
Same time?
Same area?
Same specification?
Site specifics?
Procurement method?
Same size?

Cost Planning we have to consider!

Have all the residual risks been quantified and included
Have the costs been allocated effectively between the various elements of the cost plan
Do the elemental cost estimates reflect good value rather than cheap price?
Has a cost check been carried out?


Visual Presentation - Pie chart

Figure-04



Figure-05
Visual Presentation - Bar chart

Figure-06


Figure-07








No comments:

Post a Comment

Cost Management

Are you regularly involved in construction projects where having an accurate idea of costs is important? Most people in the constructi...